WRF Addition of 4th Clarifier
Type of Project: | ||
---|---|---|
Wastewater Infrastructure at the Water Reclamation Facility | ||
Project Title: | ||
WRF Addition of 4th Clarifier | ||
Fiscal Year: | ||
2024 | ||
Project Budget: | ||
$16,200,000 | ||
Funding Source: | ||
Florida Department of Environmental Protection Clean Water Project State Revolving Fund | ||
Project Location: | ||
Water Reclamation Facility | ||
Project Status: | ||
In Progress | ||
Description: | ||
The City has contracted with Poole & Kent Company of Florida to construct a new 150-foot diameter clarifier and associated pumping and piping facilities to upgrade the existing treatment capacity of the WRF. | ||
Purpose: | ||
The new clarifier will double the solids settling capacity of the secondary treatment system. This will allow the WRF to maintain high-level disinfection and reclaimed water production under peak wet weather flow conditions. | ||
Schedule: | ||
Start Date | End Date | |
Design | November 2017 | September 2022 |
Bid Activities | September 2022 | July 2023 |
Construction | October 2023 | May 2025 |